摘要 某发电厂4×600 MW机组脱硫系统未采用回转式烟气换热器(GGH)。针对烟气采样预处理装置存在探头及加热部分腐蚀以及取样孔常被污堵的情况进行技术改造,除加装预处理装置前端保护管外,重新选择了装置的制做材料及其表面处理工艺。改进后的烟气采样预处理装置寿命长,运行效果好,且造价大幅降低,值得在同类电厂中推广使用。 The desulphurization system of 4 ×600 MW units in one power plant hadn't used generative gas heat exchanger (GGH), resulting in corrosion of sampling probe and frequent blockage of sampling holes by pollutants. For this,technical retrofit has been carried out,besides adding protective tube onto front end of the pre - treatment facility, the materials for manufacturing said facility and their surface treatment technology have been newly selected. After retrofitting, the flue gas sample pre - treatment facility has long service life, having good effectiveness in operation,decreasing cost of manufacture by a big margin,it is worth to be popularized and utilized in similar power plants.
出处 《热力发电》 CAS 北大核心 2010年第3期104-105,108,共3页 Thermal Power Generation
关键词 烟气脱硫 湿法脱硫 烟气测量 取样 预处理 flue gas desulphurization wet desulphurization flue gas measurement sampling pre - treat- ment
  • 相关文献

同被引文献12

引证文献3

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部