摘要
通过对神木县城供水工程输水隧洞施工竖井穿越高地下水砂层的不同施工工艺分析后,最终采用了成熟技术井外冷冻法堵水设计方案,一举解决了特长深埋隧洞竖井穿越高地下水砂层的技术难题。
Through the analysis of construction technique of water conveyance tunnel traversing sand layer with high groundwater of Shenmu water supply project, the design scheme of frozen blocking water in well was adopted, which solved the problem of long water conveyance tunnel traversing sand layer with high groundwater.
出处
《杨凌职业技术学院学报》
2010年第1期13-16,共4页
Journal of Yangling Vocational & Technical College
关键词
输水隧洞
竖井
高地下水砂层
井外冷冻法堵水
water conveyance tunnel shaft sand layer with high groundwater frozen blocking water in well