摘要
指出西藏电网审计电网工程过程中发现的问题,包括内部约束机制不健全、招投标手续不完善、现场签证管理不规范等及其具体表现。分析问题存在的原因,并在制度管理、设计管理、招投标管理、合同管理、施工管理、竣工结算管理等方面提出改进措施。
The existing defects and concrete manifestation in Tibet Power Grid project audit process were indicated in this paper such as unsound internal mechanism of constraint,inadequate bidding procedures,and non-standard on-site management of visa,etc.The reasons of these existing defects were analyzed.The improvement measures were put forward in some fields such as system management,design management,bidding management,contract management,billing management,and completion settlement management,etc.
出处
《华东电力》
北大核心
2010年第3期442-445,共4页
East China Electric Power
关键词
电网建设
企业管理
审计
Grid construction
business management
audit