摘要
针对仁宗海水库电站坝基采用振冲碎石桩进行处理,在施工中出现了参数特征变化较大等情况,通过现场试验,对第⑦层淤泥质壤土与第⑥层含块碎(卵)石土施工特征进行对比,对施工质量进行了定性评价,以指导现场施工。
In view of the processed gravel pile method adopted by the Renzonghai reservoir hydropower station for processing and great changes of the parameters in the process of construction and so on, through field tests, this paper makes a comparison on the silt loam on the seventh layer and pieces broken stone soil on the sixth layer, makes a qualitative evaluation the construction quality with a view to guide the construction site.
出处
《山西建筑》
2010年第13期96-97,共2页
Shanxi Architecture
关键词
淤泥质壤土
含块碎(卵)石土
施工特征
silt loam, pieces broken (eggs) stone soil, construction features