半水煤气直冷塔的计算与设计 被引量:2

Calculation and Design of Semi-Water Coal Gas Direct-Cooling Tower
下载PDF
导出
摘要 为降低合成氨装置压缩机一段入口的半水煤气温度,设计了填料式直接冷却塔,用水作为冷却剂。介绍了直冷塔的设计计算过程,包括塔的选型,气液比的确定,空速、塔径、填料高度的计算,填料层压降、喷淋密度的核算,以及塔附件的设计等。生产运行结果表明,出塔半水煤气温度由原来的42℃下降到30℃以下。 In order to reduce the inlet temperature of semi-water coal gas at the first stage of compressor in the synthetic ammonia plant,author has designed the direct cooling tower of packing type,using the water as the cooling agent,has introduced the design calculation process of the direct cooling tower,including the calculations of tower selection,determination of gas/liquid ratio,empty tower speed,diameter of tower and packing height etc.,also the checking of pressure drop of packing layer and spraying density,as well as design etc.of tower attachments.Production running result indicates that the temperature of semi-water coal gas out of the tower is reduced from the former 42 ℃ to 30 ℃ below.
作者 白二川
出处 《化肥设计》 CAS 2010年第2期11-15,共5页 Chemical Fertilizer Design
关键词 填料塔 热负荷 泛点气速 塔径 填料层压降 煤气温度 packing tower heat load flooding point gas speed diameter of tower pressure drop of packing layer coal gas temperature
  • 相关文献

参考文献2

  • 1冷士良.化工单元过程及操作[M].北京:化学工业出版社,2007第2版.
  • 2国家医药管理局上海医药设计院.化工工艺设计手册[M].北京:化学工业出版社,1996..

共引文献12

同被引文献9

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部