期刊文献+

500kV世博输变电工程启动调试方案研究 被引量:4

Study on Startup and Commissioning Scheme of 500 kV World Expo Transmission and Transformation Project
原文传递
导出
摘要 介绍了500 kV世博(静安)输变电工程主设备情况。通过仿真计算和理论分析,对启动调试中的几个重要技术问题(500 kV长电缆现场绝缘耐受试验、500 kV断路器投切操作性能及试验系统中的操作过电压水平)进行了研究,相关研究结论为该工程启动调试的顺利进行提供了有力支持。 The main equipments of 500 kV World Expo(jing-an) transmission and transformation project were presented.Based on the simulation calculation and theoretical analysis,some important technical issues(the field insulation withstand tests of 500 kV long cable,the switching operation performance of 500 kV circuit breaker and the operation voltage level of the test system) were investigated.The corresponding research conclusions provided strong support for the smooth startup and commissioning of the project.
作者 陈海波
出处 《华东电力》 北大核心 2010年第4期475-479,共5页 East China Electric Power
关键词 500kV世博输变电工程 启动调试 方案设计 500 kV World Expo transmission and transformation project startup and commissioning scheme design
  • 相关文献

参考文献2

  • 1GB311.1-1997.高压输变电设备的绝缘配合[S].[S].,..
  • 2DL/T620-1997.交流电气装置的过电压保护和绝缘配合[S].[S].,..

共引文献358

同被引文献138

引证文献4

二级引证文献406

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部