摘要
介绍了110kV蒙自变电站上按建筑一体化设计的光伏发电系统中光伏组件安装位置及电池类型的选择原则。阐释了光伏组件电气性能与建筑结构匹配的处理方式。介绍了为保证建筑一体化效果而采取的一系列措施。
This paper introduced the installation position of the photovoltaic modules in photovoltaic power generation system designed according to the building integration in 110 kV Mengzi substation,as well as the selection principle of the cell type.The treatment method to match the electrical properties of the photovoltaic modules with the building structure was expounded.A series of measures were presented to ensure the effect of the building integration.
出处
《华东电力》
北大核心
2010年第4期523-525,共3页
East China Electric Power
关键词
110KV变电站
光伏发电
建筑一体化光伏发电系统
110 kV substation
photovoltaic power generation
building-integrated photovoltaic power generation system