通过对克孜尔水库泥沙淤积情况及异重流运动条件的分析,并结合2008年汛期水库异重流排沙实例,为高含沙河流水库运行提供几点异重流排沙调度经验,以解决水库兴利与排沙的矛盾,减缓水库泥沙淤积,延长有效库容的使用年限。
Through analysis of the sedimentation and density current movement in Kezier reservoir and based on the density current de- silting case during flood season in 2008, the experience in dispatching of density current desilting is provided for high silt - laden reser- voir so as to solve the contradiction between beneficial use and desilting of reservoir, reduce reservoir sedimentation and extend the service life of effective reservoir capacity.
出处
《西北水电》
2010年第2期6-8,共3页
Northwest Hydropower
关键词
克孜尔水库
异重流排沙
调度运行
Kezier reservoir
density current desihing