特大桥梁供配电施工时序探讨

timing of power supply for construction of large bridge
下载PDF
导出
摘要 分析了特大桥梁供配电工程供电和配电的特点,结合黄埔大桥工程的实施案例,详细阐述了中压电能传输系统实施时施工时序合理安排对特大桥梁供配电工程实施的重要性。实践证明,供配电工程施工时序的合理调配,是特大桥梁工程施工质量、进度、造价控制的一个重要环节。 Analysis on features of power supply and power distribution for large bridge projects has been conducted, being combined with the implementation case of Huangpu Bridge, and introduction has been made in detail in the critical importance of reasonably - arranged timing for the power supply and power distribution of large bridge project when medium voltage transmission system executed. It has been proved that reasonable arrangement of construction timing is one of the important factors for the construction quality, progress and cost control of large bridge projects.
作者 谢光秋
出处 《广东公路交通》 2010年第1期33-36,共4页 Guangdong Highway Communications
关键词 特大桥梁 供配电 中压电能传输 施工时序 large bridge power Supply medium voltage transmission construction timing
  • 相关文献

参考文献4

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部