铁路双线软岩隧道控制大变形施工工法比选 被引量:14

Comparison and Contrast among Different Construction Methods for Double-track Railway Tunnels in Soft Ground
下载PDF
导出
摘要 为解决双线软岩隧道施工中普遍存在沉降和收敛过大、初期支护变形侵限导致拆换拱的现象,通过介绍兰渝铁路两水隧道施工中应用的几种工法,根据围岩监控量测数据分析,从安全、进度和设备利用方面进行比选,得出大拱脚台阶法比较适合于双线软岩隧道的施工。 Serious settlement, convergence and deformation always occur during the construction of double-track railway tunnels located in soft ground. 3-bench 7-step construction method, CRD construction method and enlarged-arch-foot bench method are adopted in the construction of Liangshui tunnel on Lanzhou-Chongqing railway. These three construction methods are compared in terms of safety, advance rates and equipment availability. It is concluded that enlargedarch-foot bench method is more suitable for the construction of double-track railway tunnels located in soft ground.
出处 《隧道建设》 2010年第2期134-136,共3页 Tunnel Construction
关键词 软岩隧道 变形控制 监控量测 大拱脚台阶法 tunnel in soft ground deformation control monitoring enlarged-arch-foot bench method
  • 相关文献

参考文献7

二级参考文献6

共引文献42

同被引文献124

引证文献14

二级引证文献100

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部