盖挖逆作地下工程底板大体积混凝土施工研究 被引量:15

Research on Mass Concrete Construction of Top Down Underground Structure Base Slab
下载PDF
导出
摘要 大体积混凝土施工过程中,由于其工程条件的复杂性,在温度应力作用下容易产生开裂问题。因此,基于裂缝控制对大体积混凝土施工进行温度监测及分析研究具有十分重要的意义。结合某盖挖逆作地下工程实例,论述了通过采用多种技术措施,在底板大体积混凝土施工中以跳仓法分块浇筑混凝土取代设置后浇带的工程裂缝控制方法。作者根据温度裂缝计算论证了该设计方法的可行性,并将计算值与大体积混凝土施工温度监测数据进行分析比较,充分证明本工程采用的混凝土裂缝控制方法能满足控制裂缝的要求,可供相似地下工程作参考。 During mass concrete constructions the engineering condition is usually very complex, thus, cracks are quite common to appear due to temperafure stress. Therefore, the temperature monitoring and analysis on mass concrete construction is very important for crack control. This paper studied how to use alternative bay construction together with varieties of technical measures instead of strips of post pouring concrete in a top down underground structure base slab constraction. Through analysis of thermal calculation, the authors studied the feasibility of such technical measures, and accordingly compared the computation result with numerical value of temperature monitoring. The comparison shows that this anticrack design meets the needs of construction, which can be as reference for simili ar eases.
出处 《地下空间与工程学报》 CSCD 北大核心 2010年第2期364-368,共5页 Chinese Journal of Underground Space and Engineering
关键词 大体积混凝土施工 温控计算 温度监测 跳仓法 mass concrete construction: thermal caleulation temperature monitoring alternative bay constrnetion
  • 相关文献

参考文献9

二级参考文献13

共引文献48

同被引文献60

引证文献15

二级引证文献40

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部