摘要
介绍静压管桩在湖南某大型冶炼厂房项目复杂岩溶地质中的设计及施工过程,并总结多年的工程实践经验探讨静压桩的施工工法及技术问题,为岩溶地区PHC管桩的设计和施工提供借鉴参考。
This paper mainly illustrates the application of static pressure pipe pile in karst area of the 100 thousands ton lead smelting per year of Hunan Guiyang Yinxing non-ferrous smelting Co., Ltd.,and investigates the construction method and technical problems about static pressure pipe pile.This paper can be a reference to the design of PHC pipe pile in karst area.
出处
《广东土木与建筑》
2010年第2期3-5,16,共4页
Guangdong Architecture Civil Engineering
关键词
管桩
岩溶地区
桩尖
复压
注浆
pipe pile
karst area
pile tip
re-pressing
grouting