摘要
提出了青铜峡水电站原水轮机转轮耐压试验系统存在的问题,分析了新转轮耐压系统的设计原理和功能。系统经过改造后,优点突出,运行效果良好。
Analyzes the existing problems of the withstanding pressure system for the rotating wheel of the original kaplan turbine in Qingtongxia Hydraulic Station, puts forward the design principle and the function of the new withstanding pressure system of the rotating wheel, after the system improvement, it gets better operation effect.
出处
《宁夏电力》
2010年第2期34-38,共5页
Ningxia Electric Power
关键词
水轮发电机
转轮
耐压试验系统
hydraulic turbine generator
rotating wheel
withstanding pressure system