摘要
文章介绍了新港船舶重工有限责任公司修船厂"港船浮吊2号"在改造取暖系统出现的问题,研讨其中的原因,提出了改进方案,并最终得到解决。
This paper introduces some problems during the improving of the heating system for GANG CHUAN No. 2 FLOATING CRANE of ship repair branch of TIANJIN XINGGANG SHIPBUILDING HEAVY INDUSTRY CO. , LTD. , researches the causes and puts forward the improving plan, leading to the final resolving for the problems.
出处
《中国修船》
2010年第3期33-36,共4页
China Shiprepair
关键词
浮吊
取暖
锅炉
改造
floating crane
heating
boiler
improve