特大断面隧道爆破开挖方法对比分析研究 被引量:6

The Comparison of Blasting and Excavation Method on Large Cross-section Tunnel
下载PDF
导出
摘要 文章以兰渝线关子岭隧道为依托,针对特大断面隧道V级围岩段采取光面爆破与预裂爆破两种爆破方案进行对比分析。结果表明:大断面隧道爆破开挖施工中最大位移出现在拱顶部位,施工中应加强对拱顶部位及其他关键点的监测;最大主应力出现在仰拱中点和拱腰部位,施工中须加强对仰拱中点和拱腰部位的支护。 Based on the Lan-yu line, Guanzlling tunneh the article conducts a comparative analysis on smoothing blasting method and or pre-splitting blasting method targeting V-level large cross-section rock wall.The results have shown that the largest replacement occurs at vault session during blasting construction, which needs extra monitoring as well as many other key locations.As for the main stress force, it occurs at the center of the inverted arch and hance,which also need special support.
出处 《西部交通科技》 2010年第4期50-57,共8页 Western China Communications Science & Technology
关键词 特大断面隧道 光面爆破 预裂爆破 数值分析 Large cross-section tunnel Smooth blasting Presplitting blasting Numerical analysis
  • 相关文献

参考文献10

二级参考文献16

共引文献72

同被引文献26

引证文献6

二级引证文献48

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部