北京地铁10号线盾构对周边土体扰动模拟分析 被引量:6

Simulation Analysis on Surrounding Soil Disturbance Caused by Shield Construction of Beijing Metro Line 10
下载PDF
导出
摘要 以北京地铁10号线国贸站~双井站区间隧道施工为背景,采用有限元差分程序FLAC3D建立了有限元模型,对盾构推进过程中隧道应力、变形及地表沉降规律进行研究。通过隧道上方地表横向监测点沉降、隧道中心地表沉降和地表建筑物基础沉降实测值与计算值比较,得出模拟计算结果与实际检测结果比较符合,但实际施工过程中存在复杂性和不确定因素。 Based on construction of Guomao station-Shuangjing station of Beijing Metro Line 10,tunnel stress,deformation and ground surface settlement are researched through calculation by FLAC3D software. Furthermore,some calculating results are compared with monitoring results such as transverse settlement of ground surface,ground surface settlement over vault and building foundation settlement. The comparison shows that calculating results accord with monitoring results,however,there are complex uncertain factors in practical construction.
作者 郦亮
出处 《施工技术》 CAS 北大核心 2010年第5期12-14,共3页 Construction Technology
关键词 地铁隧道 盾构施工 有限元 地表沉降 土体位移 metro tunnel shield construction finite element method ground surface settlement soil displacement
  • 相关文献

参考文献6

二级参考文献42

共引文献228

同被引文献55

引证文献6

二级引证文献34

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部