单压余热锅炉双压配置改造工程介绍

Double-pressure Configuration Modification of Single-pressure Heat Recovery Boiler
下载PDF
导出
摘要 针对比利时CMI公司单压余热锅炉效率下降的原因,阐述了GT13E2型燃气-蒸汽联合循环机组双压配置改造的重要性、可行性及双压配置改造方案,并对改造前后余热锅炉和联合循环的性能进行了对比分析,实践证明了双压配置改造是成功的,联合循环发电热效率由原来的48.5%提高到49.8%,提升了1.3%,达到设计性能基本要求。 In view of the considerable decrease in the efficiency of single-pressure heat recovery boiler manufactured by CMI, Belgium, the modification importance, feasibility and scheme of double-pressure configuration for GT13E2 gas-steam combined cycle unit are expounded. The performances of heat recovery boiler and combined cycle before and after the modification are compared and analyzed. The modification is proved successful in practice, the heat efficiency of combined cycle generation being improved by 1.3% from 48.5% to 49.8% and meeting the basic requirement of designed performance.
作者 杨家技
出处 《广东电力》 2010年第5期62-65,共4页 Guangdong Electric Power
关键词 GT13E2型联合循环机组 余热锅炉 双压配置 节能 GT13E2 combined cycle unit heat recovery boiler double-pressure configuration energy conservation
  • 相关文献

参考文献3

  • 1上海发电设备成套设计研究所.3号余热锅炉改造工程热力试验报告[R].上海:上海发电设备成套设计研究所,2004.
  • 2上海发电设备成套设计研究所.3号余热锅炉改造前性能摸底试验报告[R].上海:上海发电设备成套设计研究所,2005.
  • 3杭州锅炉集团股份有限公司.3号锅炉改造设计说明书[R].杭州:杭州锅炉集团股份有限公司,2008.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部