摘要
对越南市场环境下发电厂在建设期间电气倒送电的专业技术、施工组织、对外联络和倒送电的最后实施过程的经验和教训进行总结和分析,提出了特定环境和情况下国际工程中倒送电组织和实施的工作思路。
This paper makes an analysis of the technology, construction organization, external liaison and experiences in inverse power transmission during construction of the power plant in Vietnam, and proposes some ideas for organization and execution of inverse power transmission for overseas project under special conditions.
出处
《电力建设》
2010年第6期103-105,共3页
Electric Power Construction
关键词
发电厂
倒送电
施工
组织
实施
海外工程
power plant
inverse power transmission
construction
organization
execution
overseas project