摘要
介绍了大唐南京电厂2台660 MW机组湿法脱硫吸收塔设计方法和步骤。针对该工程无烟气旁路烟道的特点,分析了吸收塔设计需注意的问题和为提高吸收塔可靠性所采取的措施,为同类工程吸收塔设计提供参考。
Design method and procedure of wet desulfurization absorbers for 2 660 MW power units in Datang Nanjing Power Plant are being presented.Aiming at the features that the system has no by-pass flue duct,noteworthy items for the design are proposed and countermeasures therefore taken for raising reliability of the absorber put forward.This may serve as a reference for absorber design of similar engineering projects.
出处
《发电设备》
2010年第3期219-223,共5页
Power Equipment
关键词
火电厂
脱硫塔设计
无旁路烟道
防腐措施
thermal power plant
design of desulfurization absorber
no by-pass flue duct
anti-corrosion measure