摘要 结合马蹄沟大理河特大桥73号墩现浇段满堂支架施工工艺流程,分别对设计荷载箱梁底横板的强度、挠度等进行了检算,得出支架搭设安全满足施工要求的结论,为调整底模标高,确保箱梁施工安全提供了准确数据。 Combining with the construction technological process of the whole-roof prop stands in cast-in-place phase of mound No.73 of Matigou.Dali river extra large Bridge,the thesis separately checks and calculates the design load,the strength of baseboard of the box beam,deflection and so on,provides accurate data for adjusting the standard height of the baseboard and ensuring the safety of the construction of box beams.
作者 王登科
出处 《山西建筑》 2010年第17期309-310,共2页 Shanxi Architecture
关键词 连续现浇箱梁 施工工艺 强度 挠度 continuous cast-in-place box beam construction technology strength deflection
  • 相关文献

参考文献6

  • 1建筑施工碗扣式脚手架安全技术规范(征求意见稿)[S].
  • 2JGJ130-2001.建筑施工扣件式钢管脚手架安全技术规范[S].[S].,..
  • 3GB50010-2002.混凝土结构设计规范[S].[S].,..
  • 4GB50009-2001.建筑结构荷载规范[S].[S].,..
  • 5GB50017-2003.钢结构设计规范[S].[S].,..
  • 6周兴水.路桥施工计算手册[M].北京:人民交通出版社,2008.

共引文献5418

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部