摘要 系统讨论了清洁发展机制(CDM)应用于燃煤电厂汽轮机改造提高能效项目中的关键问题,从方法学适用、基准线确定、项目的额外性论证到项目经济性分析和减排量计算等方面进行了详尽的分析。以石横发电厂汽轮机改造提高能效项目为例进行分析并得出结论,为在我国开展燃煤电厂改造,提高能效CDM项目提供了技术支持。 The key issues on CDM applying to coal-fired power plant retrofit to improve efficiency were discussed systematically from views of application of methodology,determination of baseline,demonstration of project additionality,investment analysis,and CO2 mitigation calculation from the project and so on.The energy efficiency improvement project of Shandong Shiheng power plant was analyzed and the conclusions were given,which provide technical support for implementing coal-fired power plant energy efficiency improvement CDM projects in China.
出处 《华东电力》 北大核心 2010年第5期736-739,共4页 East China Electric Power
关键词 电厂改造 清洁发展机制 温室气体减排 基准线 power plant retrofit CDM greenhouse gas mitigation baseline
  • 相关文献

参考文献5

二级参考文献11

  • 1李俊峰,刘迎春.《京都议定书》生效给我国带来的影响[J].节能与环保,2005(2):11-12. 被引量:4
  • 2吕学都 刘德顺.清洁发展机制在中国[M].清华大学出版社,2004..
  • 3姜克隽,于胜民,胡秀莲.清洁发展机制(中文版)[M].北京:气象出版社,2003.
  • 4中国电力年鉴编委会.2004年中国电力年鉴[M].北京:中国电力出版社,2005.
  • 5中国电力企业联合会.电力建设项目概预算定额编制指南[M].北京:中国电力出版社.2005.
  • 6中国气候变化国别研究编写组.中国气候变化国别研究[M].北京:清华大学出版社.2000.
  • 7中国统计年鉴编辑部.2004年中国统计年鉴[M].北京:中国统计出版社.2004.
  • 8Revision to the approved consolidated baseline methodology ACM0006. Consolidated methodology for grid-connected electricity generation from biomass residues [ EB/OL]. http:// cdm. unfccc. int/UserManagement/FileStorage/CDMWF _ AM KH6OFAWYAX8K8ILKVFFKTZ0M6Z2YBD.
  • 9中国清洁发展机制网.关于电网排放因子的补充说明[EB/OL].http://cdm.ccchina.gov.cn/web.
  • 10《中国电力年鉴》编辑委员会.中国电力年鉴[M].中国电力出版社,2004.

共引文献11

同被引文献13

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部