摘要
通过对照方家山核电工程前期可行性研究的24份支持性文件工作过程,对前期可行性研究支持性文件工作过程进行了分析,明确了核电建设项目可行性研究所应取得的27份支持性文件以及派生的相关报告;针对8份具有代表性的支持性文件工作过程进行了详细阐述。通过分析认为,核准制下取得20余份可行性研究支持性文件和相关专题论证增长了项目建设周期。建议可行性研究支持性文件从经济规划、城市规划、土地规划以及核安全、环境等9个方面的主管部门取得相关意见即可。
This paper analyzed the process for the approval of the 24 backup documents during the feasibility study stage of Fang Jiashan nuclear power plant,and defined the 27 backup documents and derivative documents that should be obtained during feasibility study stage for nuclear power construction projects,and finally expound the 8 representative documents in detail.The analysis showed that the process for the approval of all the backup documents under the Approval System prolonged the project construction period.It recommended that the backup documents can be obtained from the nine departments,such as those involved in the economic planning,urban planning,land use planning and nuclear safety,as well as environmental protection.
出处
《核动力工程》
EI
CAS
CSCD
北大核心
2010年第3期136-142,共7页
Nuclear Power Engineering
关键词
核电工程
可行性研究
方家山
支持性文件
Nuclear power engineering
Feasibility study
Fang Jiashan
Backup documents