摘要 针对浙江北仑发电厂3期输煤系统自投产以来堆场总容量一直无法有效提高的问题,从堆场的煤种数量,堆煤长、宽、高4个因素进行分析,找出堆场总容量偏低的主要原因。同时结合现场生产实际,经过详尽的分析和计算,提出了在已有的堆场面积上,合理设定和提高堆场容量的改进方案。 According to the problem in which the total capacity of storage yard of phase three coal handling system of Zhejiang Beilun Power Plant has been unable to effectively improve since being put into production,the analysis on the coal kinds,and coal pile length,width,height is conducted,and the main reason for the lower general capacity of storage yard is found out. At the same time,in combination with the on-site production actuality,through detailed analysis and calculation,the improvement scheme to rationally set and improve the capacity of storage yard is proposed on the existing storage yard area.
作者 王轶
出处 《起重运输机械》 2010年第6期85-88,共4页 Hoisting and Conveying Machinery
关键词 输煤系统 堆场总容量 改进方案 coal handling system total capacity of storage yard improvement scheme
  • 相关文献

参考文献2

  • 1邵明亮,于国飞,耿华,等.斗轮堆取料机[M].北京:化学工业出版社,2007.
  • 2郑体宽.热力发电厂[M].北京:中国电力出版社,1997..

共引文献100

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部