复杂地质条件下千米竖井快速施工技术研究 被引量:6

Study on Rapid Construction Technique of 1000-Meter Shaft under Complicated Geological Condition
下载PDF
导出
摘要 金川矿山18行副井工程井筒深达1 165.5 m,施工时频遇断层、严重涌水等复杂的不良地质地层,工程中采用快速施工技术,对凿井机械化配套设备进行多项改进,并新引用电子配料搅拌系统、非电起爆系统、供风供水聚丙烯管材系统和多台稳车集中控制系统等先进技术,建成的竖井质量评为优良,为千米竖井累积了丰富的施工技术和管理经验。 Shaft engineering at Jinchuan Mine No.18 Level,with pit shaft 1165.5m deep,is frequently encounter with poor geological conditions such as fault and serious water burst during construction.Drilling mechanical support equipment is given various improvements with rapid construction technique during constructionand advanced technology such as electric mixing system,non-electric initiation system,polypropylene piping system for air and water supply and multiple stability centralized control system are newly introduced.The completed shaft is evaluated excellent,which accumulates rich construction technology and management experience for 1000-meter shaft.
出处 《路基工程》 2010年第3期236-238,共3页 Subgrade Engineering
关键词 机械化凿井设备 千米竖井 快速施工 改进 mechanical drilling equipment 1000-meter shaft rapid construction improvement
  • 相关文献

参考文献7

二级参考文献11

共引文献62

同被引文献20

引证文献6

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部