水利水电工程全圆断面隧道衬砌模板比选 被引量:2

Selection of Lining Formworks for Full-circular Cross-section Tunnels of Water Conservancy and Hydropower Projects
下载PDF
导出
摘要 通过南水北调05,06标段施工中使用的针梁式模板台车、组合模板和简易模板台车的施工工艺和施工成本的分析比较,说明在水利水电工程全圆衬砌施工过程中,通过比选确定衬砌模板形式,对项目成本控制以及提高衬砌施工进度起着关键性作用。 Needle-type formwork jumbos, composite formworks and simple formwork jumbos are used in the construction of No. 05 and No. 06 bid sections of South-to-North Water Transfer Project. These three types of formworks are compared in terms of constructin techniques and construction cost on basis of the engineering experience. It is concluded that selection of proper formworks for the full-circular cross-section tunnels of water conservancy and hydropower projects has great significance for the construction cost control and the improving of the lining progress.
出处 《隧道建设》 2010年第3期327-330,343,共5页 Tunnel Construction
关键词 水利水电 全圆衬砌 针梁式液压模板台车 简易模板台车 组合模板 water conservancy and hydropower projects full-circular lining needle-type hydraulic formwork jumbo simple formwork jumbo composite formwork
  • 相关文献

参考文献10

二级参考文献4

共引文献13

同被引文献13

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部