摘要
结合深圳星河龙岗填湖工程,通过现场试验、监测、检测,介绍深水湖泊深厚淤泥高填方地基的填筑方法、填料要求,地基承载力、变形模量、沉降的控制和保证措施等对填湖地基的设计和施工具有一定的参考意义。
Combining with the Xinghelonggang filling lake engineering in Shenzhen,by field testing,monitoring and detecting,the filling method and filler requirement of deep and thick silt high embackment in deep lake were introduced.The bearing capacity of foundation,deformation modulus,the controlling of settlement and ensure measurements have a certain reference meaning to the design and construction of filling lake foundation.
出处
《山西建筑》
2010年第18期74-75,共2页
Shanxi Architecture
基金
深圳星河房地产公司
深圳地质局联合资助项目
关键词
强夯法
强夯置换法
地基处理
dynamic consolidation
dynamic replacement method
foundation treatment