摘要
论述了高铁矿对浸出系统生产影响的几个方面,并对这些影响问题提出工艺控制条件,采取了处理控制对策,取得较好的生产效果。
Discusses the high-iron zinc concentrates on the leaching effects of several aspects of system production.These effects and conditions of process control issues.Process control measures taken to achieve better production results.
出处
《甘肃冶金》
2010年第3期59-61,共3页
Gansu Metallurgy
关键词
黄钾铁矾处理高铁矿
浓密澄清
中上清率
沉矾
jarosite process
high-iron zinc concentrates
thickener clarification
rate of neutral leaching solution
precipitation jarosite