摘要
某高填方场地平整工程中,包含平整场地中修建道路。但由于道路工程路基施工工序与场地平整工序未协调进行,导致路基出现严重开裂。该文通过对该工程的施工过程和开裂现象进行阐述,从而揭示高填方场地平整工程若包含道路路基施工,其路基施工与场地平整施工之间的工序安排就显得十分重要。
There are the roads to be constructed in the leveling work of a high filling ground. Due to the construction sequence between high filling roadbed and high filling ground being not coordinated, the bad cracks appear on the roadbed. The article sets forth the construction process and the cracking phenomena of this project so as to open out the significance of sequence arrangement between the roadbed construction and the ground leveling construction if the construction of roadbed is included in the high filling ground leveling project.
出处
《城市道桥与防洪》
2010年第6期168-170,共3页
Urban Roads Bridges & Flood Control
关键词
高填方
场地平整
路基
施工工序
high filling, ground leveling, roadbed, construction sequence