高填方路基与高填方场地平整之间的施工顺序实例分析 被引量:3

Analysis of Construction Sequence between High Filling Roadbed and High Filling Ground Leveling
下载PDF
导出
摘要 某高填方场地平整工程中,包含平整场地中修建道路。但由于道路工程路基施工工序与场地平整工序未协调进行,导致路基出现严重开裂。该文通过对该工程的施工过程和开裂现象进行阐述,从而揭示高填方场地平整工程若包含道路路基施工,其路基施工与场地平整施工之间的工序安排就显得十分重要。 There are the roads to be constructed in the leveling work of a high filling ground. Due to the construction sequence between high filling roadbed and high filling ground being not coordinated, the bad cracks appear on the roadbed. The article sets forth the construction process and the cracking phenomena of this project so as to open out the significance of sequence arrangement between the roadbed construction and the ground leveling construction if the construction of roadbed is included in the high filling ground leveling project.
作者 马超明
出处 《城市道桥与防洪》 2010年第6期168-170,共3页 Urban Roads Bridges & Flood Control
关键词 高填方 场地平整 路基 施工工序 high filling, ground leveling, roadbed, construction sequence
  • 相关文献

参考文献1

  • 1JTJ017-96.公路软土地基路堤设计与施工技术规范[S].[S].,..

共引文献337

同被引文献5

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部