本文结合重庆港主城港区寸滩作业区二期集装箱多用途码头泊位及重箱堆场工程项目,介绍了码头框架结构上部面板的吊架施工全过程,包括施工方法比选,支撑体系及模板安装,钢筋绑扎,混凝土浇筑、养护,支架拆除及质量检验,为今后的类似工程提供参考。
Combined with multipurpose container berths and heavy containers yard in the second phase project of Cuntan international container terminal in Chongqing,this paper introduces the whole process of hanger construction in Slab upper upright frame wharf,specifying comparing and selecting of construction methods,installing of support system and formwork,assembling reinforcement,concrete pouring and curing,removing support and inspecting quality,thus providing useful references for the future similar projects.
出处
《重庆建筑》
2010年第6期50-52,共3页
Chongqing Architecture
关键词
吊架法
码头集装箱平台
面板
施工技术
hanger
platform of container terminal
slab
construction technology