摘要
通过把模糊空间间歇时间和模糊工艺间隙时间等新概念引入搭接作业网络图,并应用模糊集理论构造了一类含模糊完成期的搭接作业模糊网络模型,提出了一套求解该模型、计算模糊空间间歇期、模糊工艺间歇期和模糊节点时间参数的模糊算法。
In the paper, by proposing the new concepts of fuzzy spatial period and fuzzy technological peroid, a sort of fuzzy network model for lap works is developed, and by applying fuzzy set theory,the fuzzy algorithm of solving the model,named α algorithm,is put forward.
出处
《铁道学报》
EI
CAS
CSCD
北大核心
1999年第2期89-93,共5页
Journal of the China Railway Society