摘要
印度尼西亚一国际工程机组无启备变设计,因厂用电的单一性而导致无法实施发变组零起升压试验。在机组整套启动前,通过解除发电机引出端与封闭母线的连接,改变运行方式实现并列点两侧的电压互感器同电源核相,可以较好地解决此问题,且能够节省机组整套启动的试验时间,简化整套启动试验内容,具有一定的经济性。
There is no start-up standby transformer design in an Indonesia international project, the voltage of generator-transformer group can not be boosted from zero due to the fragility of the auxiliary power. However, this problem can be solved by disconnecting generator outlet terminal and isolated-phase busbar ( IPB ) before the startup of unit and then verifying the sequence and polarity of generator-transformer group as described above, which can also shorten the testing time and simplify the test content for the startup of unit in an economical way.
出处
《电力系统保护与控制》
EI
CSCD
北大核心
2010年第13期133-134,139,共3页
Power System Protection and Control
关键词
准同期
核相
国际工程
同电源
经济性
full synchronizing
sequence verifying
international project
same power supply
economical efficiency