摘要
根据主井装载系统由于装载、信号监控及控制系统程序自身有缺陷,经常因为信号操作工误操作、开关坏等原因,影响系统安全运行。针对存在的问题系统分析,提出了增改装载控制程序解决了问题,优化完善了系统流程,有效避免了主井装载系统故障的发生,使主井自动化装煤系统运行更安全可靠。
The main shaft loading system as loading,signal monitoring and control system program itself flawed,because the signal operator frequent misuse,switch bad,have affected the safe operation of the system.System for the problems presented by modified control procedures are set out to solve the problem,improved system optimization process,the main shaft loading avoid the occurrence of system failure,so the main shaft automation coal loading system run more secure.
出处
《煤炭技术》
CAS
北大核心
2010年第7期50-51,共2页
Coal Technology
关键词
主井
装载
流程
PLC
main shaft
loading
process
PLC