自2007年上半年开始,国内建材及人工等市场价格均出现了大幅上涨。为确保工程顺利进行,东部沿海高速公路项目参照市建设局和省建设厅相关文件,确定材料及人工调差费用由代建单位全额支付给施工单位。本文针对第一标段人工和材料的调差计算方法提出个人的一些看法供研讨。
Since the first half of 2007, domestic building materials and artificial market prices are rising sharply. To ensure that project smoothly, the eastern coastal highway project according to the municipal construction bureau and province construction department, materials and related documents by artificial adjustment differential fees paid to the construction unit construction units. Aiming at the first section of the manual and material computation methods of differential some personal views for discussion.
出处
《价值工程》
2010年第20期91-91,共1页
Value Engineering
关键词
人工
材料
上涨
调差
artificially
materials
rose
adjustable difference