吸收塔是电厂烟气脱硫装置中的关键性设备。倒装法由于在降低费用、缩短工期、减少高空作业量、不受场地限制等方面具有显著的优点,因而在吸收塔的施工技术中被广泛采用。
The absorption tower is a critical part of thermal plant flue gas desulfurization. Reverse erection of absorption tower will lower the cost, shorten the time limit of project and reduce operation in height, without limiting by the functioning site. So it is applied widely in absorption tower engineering.
出处
《广东输电与变电技术》
2010年第4期36-39,共4页
Guangdong Power Transmission Technology
关键词
火力发电厂
烟气脱硫
吸收塔
倒装法
Thermal pant Flue gas desulfurization Absorption tower Reverse erection