摘要
葛野川抽水蓄能电站是日本东京电力公司新建的第8座抽水蓄能电站。位于山梨县境内,电站总装机容量1600MW,装有4台400MW的水泵水轮发电机组。有效水头为714m,最大流量280m3/s。电站工程于1993年1月开工,计划1999年7月第1期工程竣工。届时有2台机组投入商业性运行。文中叙述了该电站的设计和施工的技术特点。
The Kazunogawa pumped storage hydroelectric power station is the eighth one of similar power stations in Tokyo Electric Power Company. It is located in Shanli county. The total installed capacity of this power station is 1 600 MW, there are four 400 MW pump-turbine units. Its effective head is 714 m, the maximum discharge is 280 m 3/s. This project started working in January 1993, the first phase engineering is scheduled to complete in July 1999. At that time, two units will be put into commercial operation. The design and the construction characteristics of this hydroelectric power station are described in this paper. [
关键词
抽水蓄能电站
碾压混凝土坝
设计
施工
Pumped storage hydroelectric power station Pump-turbine Underground power house Roller compacted concrete dam Tunnel boring machine Kazunogawa