摘要
以205国道莱芜段铺筑沥青混凝土路面的压实工序为例,分析了碾压工艺中易出现的质量问题及其影响因素,介绍了压实设备的选型及碾压工艺中对碾压温度,压路机振频、振幅选择,碾压顺序等方面的控制方法。
Taking the asphalt pavement compaction procedure of 205 national road Laiwu section for example, the problems occured during compaction and the influencing factors are analysed, the equipment selection, the control method of compaction temperature, vibratory frequency and amplitude selection, and the compaction sequence are introduced.
出处
《筑路机械与施工机械化》
北大核心
1999年第1期22-24,共3页
Road Machinery & Construction Mechanization