摘要
主要介绍了严桥支线C10标J40-1,J40-2两个工作井21.6 m深基坑降承压水施工对临近磁悬浮轨道交通高架线路保护控制措施,对基坑开挖突破常规基坑降水等作了详细的叙述,为今后复杂环境下降水施工提供了经验。
The introduction on two working wells: J40-1 and J40-2 on Yan Bridge branch line C10,and on the protecting and control measures of elevated line of the magnetic levitation rail traffic through the constructions of the 21.6 m deep foundation pit dewatering confined water are the main points of this thesis that expounds the foundation pit excavation breaking out the regular foundation dewatering and etc.,which provides experience for the dewatering constructions under complicated environment in the future.
出处
《山西建筑》
2010年第22期105-106,共2页
Shanxi Architecture
关键词
深基坑施工
磁悬浮保护
非常规降水
安全控制
deep foundation pit construction
the protection of magnetic levitation
irregular dewatering
security control