摘要
以240m烟囱工程为例,介绍电动提模施工技术受力模型、工艺原理以及在模板系统、平台系统、垂直运输系统等方面的优化。该技术先进可靠、可操作性强、施工效率高、劳动强度低,并且技术、经济、社会效益显著。
The 240m-high chimney project is taken as an example lifting force model, technical theory and optimizations in formwork transportation system, etc. This technique is advanced and reliable, to mainly introduce electric formwork system, platform system and vertical have high operability, high construction efficiency, low labor intensity, obvious technical, economic and social benefits
出处
《建筑技术》
北大核心
2010年第8期720-722,共3页
Architecture Technology
关键词
筒壁
电动提模
同步
独立微调
chimney wall
electric formwork lifting
synchronous
individual fine tuning