摘要
狮子坪水电站厂房交通洞覆盖层组成物质大小悬殊,分布不均匀,结构松散且夹有大量孤石,具架空结构,成洞条件极差。对厂房交通洞覆盖层的性状、成因及成洞施工方法、主要问题及处理措施进行了分析。
The access tunnel to powerhouse at Shiziping hydropower station has a poor tunneling conditions because the overburden has such characteristics : the heterogeneity of the particle,the nonuniformity of the distribution,the uneven of the structure,containing a plenty of boulders and space frame.Therefore,the properties,the cause and construction methods,the major problems and the treatment measures of the overburden at the access tunnel to powerhouse are discussed.
出处
《四川水力发电》
2010年第4期17-18,27,共3页
Sichuan Hydropower
关键词
狮子坪水电站
厂房交通洞
覆盖层
成洞条件
Shiziping hydropower station
access tunnel to powerhouse
overburden
tunneling conditionl