从钢管格构—贝雷组合临时支撑体系以及桥面、桁架—桁拱钢结构安装三个方面,介绍了上海嘉定昌吉东路蕴藻浜大桥工程的"先梁后拱"施工工艺,施工结果显示满足规范要求。
From the steel pipe lattice-beret combination temporary system, the bridge surface, the truss and truss steel structure installation, the paper introduces the beam-first and arch-second construction craft in the Yunzaobang Bridge on Changji east road of Jiading in Shanghai, and displays the regulation of the construction results.
出处
《山西建筑》
2010年第24期335-336,共2页
Shanxi Architecture
关键词
下承式
拱桥
先梁后拱
桥梁施工
through type, arch bridge, beam-first and arch-second, bridge construction