摘要
在山区进行采选工程建设时,由于地形的限制,往往要采用半埋式井塔。半埋式井塔的施工要考虑与平硐运输、地形地质等条件的配合,因此,其施工与完全在地面以上进行的井塔施工差别很大。半埋式井塔的施工经验可供类似工程参考。
When the engineering construction of mining and ore dressing is being carried out in the mountainous district,it often adopt semi-buried shaft tower due to the topographic limit.Because the construction semi-buried shaft tower should consider adit transportation,topography,geology and other conditions,semi-buried shaft tower construction is very different from the construction on the ground.This paper provides reference for similar engineering construction through the construction experience of semi-buried shaft tower.
出处
《中国矿山工程》
2010年第4期26-28,共3页
China Mine Engineering
关键词
半埋式井塔
平硐
大模板
爬升脚手架
semi-buried shaft tower
adit
large formwork
climb scaffold