摘要
对北仑二期3×600MW机组,在500kV开关站发生电气故障时如何来启动机组的厂用电切换,提出了逻辑修改方案,并对修改后逻辑的优缺点进行了探讨。
How to initiate switchover of unit auxiliang supply when the electrical fault take place in set -- upsubstation of Beilan power plant phase 11 (300 x 600 MW), The modification lagic scheme is pro~ and thisscheme is discussed.