以巴基斯坦QICT二期项目为例,分别对大直径钢管桩在复杂地质条件下的设备选型、钻打结合施工方法和最终承载力复核进行了分析和探讨。
Taking Qasim International Container Terminal Phase 2 Project in Pakistan as an example,this paper probes into the selection of construction equipment,construction method of drilling and driving,as well as the checking of the ultimate bearing capacity for the large-diameter steel pipe piles installed under complicated geologic conditions.