摘要
输水系统是水电站工程重要的组成部分,尤其是对于高水头引水式电站,输水系统的水头损失计算显得更加重要。结合南德瑞瓦图水电站工程实例,探讨输水系统水头损失计算中应该注意的问题,对喷混凝土的糙率和马蹄形隧洞的水头损失计算进行了论述,为其他水电站输水系统的水头损失计算提供参考。
Water conveyance system is an important part of a hydropower station,especially to high head and diversion type station,in which head loss calculation is more important.This text discusses the problems to be attentioned in head loss calculation of water conveyance system in combination with the Nadarivatu Renewable Energy Project.Calculation on shotcrete roughness and head loss of horse-shoe tunnel is discussed to provide reference for head loss calculation in other projects.
出处
《水利水电工程设计》
2010年第3期45-46,52,共3页
Design of Water Resources & Hydroelectric Engineering
关键词
输水系统
糙率
水头损失
南德瑞瓦图水电站
water conveyance system,roughness,head loss,Nadarivatu Renewable Energy Project.