铜山选矿厂设计方案的研究 被引量:2

Study on designing scheme for concentrator of Tongshan Mining Company
原文传递
导出
摘要 介绍了铜山矿现用选矿厂房和设备的现状以及破磨生产流程,提出改用新型球磨机即可单台完成破磨生产任务;将破磨、铜硫浮选、铁磁选和尾沙输送安装在现用地基稳固的碎矿和球磨厂房内,利用现有设施实施矿浆自流的方案。它与半自磨加球磨和平地建新选矿厂的方案相比,基建费用减少,生产单耗降低,还可减少钢球、材料和备件的消耗。 The paper introduced the current building and equipments and the grinding process flow of Tongshan Mining Company, and proposed to use single new-type ball mill to accomplish grinding operation. Moreover, the grinding, copper-sulfur flotation, iron magnetic concentration and tailings transportation equipments were installed in the existing crushing and grinding building with sound foundation, thus the automatic flow of slurry was realized with present facilities. Contrasted with the addition of grinding ball into semi-autogenous grinding mill and establishment of concentrator on a new floor area, the cost of capital construction and unit power consumption reduced, and the consumption of grinding ball, material and spare parts decreased as well.
作者 唐新民
出处 《矿山机械》 北大核心 2010年第17期94-98,共5页 Mining & Processing Equipment
关键词 选矿厂 新型球磨机 矿浆自流 设计方案 concentrator new-type ball mill automatic flow of slurry designing scheme
  • 相关文献

参考文献3

二级参考文献10

共引文献40

同被引文献9

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部