期刊文献+

MPS275辊盘式中速磨煤机安装中的问题及处理 被引量:1

Problems and Treatment of MPS275 Disc-roller Medium-speed Mill
原文传递
导出
摘要 天津北疆一期2×1000MW机组工程安装了6台型号为MPS275辊盘式中速磨煤机,该磨煤机与300、600MW机组中速磨煤机相比结构有一定的变化,而且体积和单件质量较大,在运输、安装中易出现变形,造成组合、安装中出现较大误差。在施工现场采取了基础台板变形和下架体偏差的控制,喷嘴环间隙和分离器施工方案的调整等措施,很好地解决了工程中出现的问题,顺利完成了磨煤机的安装施工任务。 Six MPS275 disc-roller medium-speed mills were installed for the two 1 000 MW units of Tianjin Beijiang Phase 1 Power Plant.Compared to the medium-speed mills for 300 MW or 600 MW units,this kind of mill is larger in volume and weight,and is prone to deformation during transportation and installation,and as a result,larger errors occur in the process of assembly and instillation.Measures were taken on the construction site,including control of the deformation of the foundation bedplate and the deviation of the scaffold,adjustment of the nozzle ring clearance,and construction method adjustment for divider,which have well solved the above-said problems.
出处 《电力建设》 2010年第9期91-93,共3页 Electric Power Construction
关键词 中速磨煤机 设备安装 磨辊 台板 磨盘密封环 喷嘴环 medium-speed mill equipment installation roller bedplate disc sealing ring nozzle ring
  • 相关文献

参考文献2

二级参考文献26

共引文献27

同被引文献1

  • 1葛志祺.《机械零件设计手册》[M].北京:冶金工业出版社,1994.

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部