岗南水库泄洪洞进口2500kN固定卷扬式启闭机吊装施工技术

Lifting Construction Technique of 2500kN Fixed Winch Hoist in the Inlet of Spillway Tunnel of Gangnan Reservoir
下载PDF
导出
摘要 岗南水库除险加固工程,泄洪洞进口2500kN卷扬式启闭机吊装,位于水面以上25m,无现成吊装设备可用。笔者等经过研究,确定采用自制门形钢桁架,安装2台卷扬启闭机起吊的吊装方案,将启闭机拆解为机架、卷筒和减速器三大部分,起吊重量最大为卷筒部分,重18t。成功地完成了吊装任务,为同类设备吊装积累了施工经验。 For risk remove and engineering reinforcement of Gangnan Reservoir, lifting of 2500kN winch hoist in the inlet of spillway tunnel 25m above the water line cannot be realized without active lifting equipment. Therefore, the modified portal steel truss was adopted. The lifting Scheme was chosen with same lifting of two winch hoists. The hoist compose of rack, reel and speed reducer. The heaviest part is reel with the weight about 18 ton. By those techniques, lifting task is finished successfully. Construction experience is accumulated for the lifting of the similar equipment.
出处 《南水北调与水利科技》 CAS CSCD 2010年第A01期60-61,67,共3页 South-to-North Water Transfers and Water Science & Technology
关键词 启闭机吊装 钢桁架 压杆稳定 岗南水库 winch lifting steel truss pressure bar stabilization Gangnan Reservoir
  • 相关文献

参考文献4

  • 1SL74-95.水利水电工程钢闸门设计规范[S].[S].,..
  • 2DL/T5018-94.水利水电工程钢闸门制造安装及验收规范[S].[S].,..
  • 3SD267-88,水利水电建筑安装安全技术工作规程[S].
  • 4GB50017-2003.钢结构设计规范[S].[S].,..

共引文献2121

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部