广交会大厦核心筒分片式爬模施工技术 被引量:8

Construction Technology of Climbing Formwork by Pieces for Core-tube of CIEF Building
下载PDF
导出
摘要 广交会大厦为钢框架-混凝土核心筒结构体系。工程创新采用分片式液压爬模和爬模初始安装技术,即结合核心筒混凝土浇筑和上层钢筋绑扎情况,分片爬升内外模板,解决了外伸牛腿对整体爬升的不利影响;施工中预留安装孔洞,利用爬模的大钢模板完成首层施工后安装爬模架体和模板,改进了先用普通模板施工两层墙体作承载体的方法,令整个爬模系统灵活、适用性强、提高工效。 CIEF building is designed as steel frame and concrete core-tube structure.Multi-pieces hydraulic climbing formwork and initial installation technology is innovatively used in the project.Combining with concrete pouring and upper layer steel bars construction,internal and external formworks are lifted by pieces,and the extended bracket influence to integral lifting is avoided.Through presetting installation holes,the first floor can be constructed using large steel formwork of the climbing formwork,and then climbing formwork system can be installed,therefore traditional method of constructing two storey structure as bearing body with common formwork are improved.So the system is more flexible,suitable,and effective.
出处 《施工技术》 CAS 北大核心 2010年第9期99-101,共3页 Construction Technology
关键词 广交会大厦 核心筒 液压爬模 分片爬升 初始安装 CIEF building core-tube hydraulic climbing formwork climbing by pieces initial installation
  • 相关文献

参考文献5

  • 1北京土木建筑学会.模板与脚手架工程施工技术措施[M].北京:经济科学出版社,2005.
  • 2张良杰.莫斯科联邦大厦墙柱液压爬升模板施工技术[J].施工技术,2007,36(2):26-29. 被引量:5
  • 3南通四建集团有限公司.JGJ183-2009液压升降整体脚手架安全技术规程[s].北京:中国建筑工业出版社,2009.
  • 4北京市建筑工程研究院.Q/BCJ03-2001建筑施工分体式附着升降脚手架[S].北京,2001.
  • 5北京钢铁设计研究总院.GB50017-2003钢结构设计规范[S]北京:中国计划出版社,2003.

共引文献9

同被引文献24

引证文献8

二级引证文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部