摘要
针对桂东电力股份有限公司下属昭平、巴江口、下福等中小型水电站向外远距离输送电力时存在电站端电压偏高、用户端电压偏低的问题,分析其原因,结合实际提出相应对策,实践证明效果良好。
The mid-or small-scale hydropower stations under Guangxi Guidong Electric Power CO.,LTD such as Zhaoping,Bajiangkou and Xiafu etc.had seen the problem of voltage being too high at power station side and too low at user side where long-distance power transmission is required.Based on analysis of the causes,the author put forward corresponding solutions combined actual conditions,rendering good effects.
出处
《广西水利水电》
2010年第4期78-80,共3页
Guangxi Water Resources & Hydropower Engineering
关键词
中小型水电站
电力
远距离输送
问题
对策
Mid-or small-scale hydropower station
electric power
long-distance transmission
problem
solution