航空制造多项目优先级模糊综合评价方法 被引量:3

A Fuzzy-integrated Approach to Efficiently Evaluate the Priority of Multiple Projects for Aviation
下载PDF
导出
摘要 针对企业多项目并行执行时可能出现冲突,提出多项目冲突优先的模糊综合评价方法,通过建立优先级评定矩阵、分类分解评判因素的层次结构、建立评价集、确定因素权重,最后建立多项目优先级模糊综合评价矩阵,从而确定项目的优先级关系,实现项目冲突消解。并以某型飞机机翼和机身制造项目为例验证了方法的可行性和正确性。 There are muhiple projects in the manufacturing enterprise at the same time. During the process of imple- menting the concurrent projects, some conflicts among these projects may occur. In order to eliminate these conflicts, this paper presents a fuzzy- integrated approach to efficiently evaluate the priority of concurrent multiple projects. The ap- proach includes the following steps:building priority matrix;classifying the evaluating factors and constructing hierarchy of the factors ; constructing the set and importance of factors ; and getting the matrix evaluating the priority of concurrent multiple projects. Then the priority of concurrent multiple projects can be achieved. We can eliminate the conflicts among these projects by the priority. The approach is applied successfully to evaluate the priority between the wing sub- project and fuselage sub- project for an aircraft project.
出处 《航空计算技术》 2010年第5期44-47,共4页 Aeronautical Computing Technique
关键词 多项目 优先级 模糊评价 冲突消解 multiple projects priority fuzzy evaluation conflict elimination
  • 相关文献

参考文献7

  • 1PK Dey. Integrated project evaluation and selection using multiple- attribute decision - making technique [ J ]. International Journal of Production Economics,2006,103( 1 ) :90 - 103.
  • 2Scot E Fricke, Aaron J Shenhar. Managing Multiple Engineering Projects in a Manufacturing Support Environment [ J]. IEEE Transactions on Engineering Management. 2000, 47 (2) :258 -268.
  • 3KM Wang, CK Wang, C Hu. Analytic hierarchy process with fuzzy scoring in evaluating multidisciplinary R&D projects in China[ J]. IEEE Transactions on Engineering Management, 2005,52 ( 1 ) : 119 - 129.
  • 4F Tuysuz, C Kahraman. Project risk evaluation using a fuzzy analytic hierarchy process: An application to information technology projects [ J ]. International Journal of Intelligent Systems. 2006,7 ( 24 ) :385 - 394.
  • 5PN Smith. A comparison of some fuzzy relation- based linguistic preference models for multiple- factor project assessment[ J ]. Cybernetics and Systems, 2005,36 ( 7 ) : 667 - 686.
  • 6HQ Pan, CH Yeh. Fuzzy project scheduling with multiple objectives[ A]. Lecture Notes in Artificial Intelligence (PRICAI 2004: Trends in Artificial Intelligence, Proceedings ), 2004,3157 : 1011 - 1012.
  • 7徐玖平,胡知能等.运筹学[M].北京:科学出版社,2004.

共引文献34

同被引文献26

引证文献3

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部